Q.1

Mile Stone charts were invented in the year of

  • 1910
  • 1920
  • 1930
  • 1940
  • 1950
Q.2

Which one of the following represents an activity

  • excavation for foundation
  • curing of concrete
  • setting of question paper
  • preparation of breakfast
  • all the above.
Q.3

Pick up the incorrect statement from the following:

  • An activity of a project is denoted by an arrow on the net work
  • The tail of the arrow indicates the start of the activity
  • The head of the arrow indicates the end of the activity
  • The arrows are drawn to scale from left to right
  • Each activity consumes a given time.
Q.4

The difference between the time avail-to do a job and the time required to do the job, is known as

  • event
  • float
  • duration
  • constraint.
Q.5

The technique for establishing and maintaining priorities among the various jobs of a project, is known

  • Event flow scheduling technique
  • Critical ratio scheduling
  • Slotting technique for scheduling
  • Short interval scheduling.
Q.6

The object of technical planning, is

  • preparation of specifications
  • preparation of estimates
  • initiating the procurement action of resources
  • taking remedial action for likely bottleneck in the execution
  • all the above.
Q.7

The salient feature of functional organisation is

  • strict adherence to specifications
  • separation of planning and design part
  • each individual maintains functional efficiency
  • work is properly planned and distributed
  • all the above.
Q.8

Frederick W. Taylor introduced a system of working known as

  • line organisation
  • line and staff organisation
  • functional organisation
  • effective organisation.
Q.9

Critical path method

  • is an improvement upon bar chart method
  • provides a realistic approach to daily problems
  • avoids delays which are very common in bar charts
  • was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957
  • All the above.
Q.10

CPM is

  • synthesising in concepts
  • is built of activities oriented programme
  • is based on time estimate
  • is used for repetitive works
  • all the above.
Q.11

An Executive Engineer may have powers upto

  • Rs. 25,000
  • Rs. 50,000
  • Rs. 100,000
  • Rs. 200,000
  • Rs. 500,000
Q.12

The main principle of an organisation, is

  • unity of command
  • cohegency
  • effective control at all levels
  • delegation of authority
  • all the above.
Q.13

Military organisation is known as

  • line organisation
  • line and staff organisation
  • functional organisation
  • none of these.
Q.14

The performance of a specific task in CPM, is known

  • Dummy
  • Event
  • Activity
  • Contract.
Q.15

Pick up the PERT event from the following:

  • Digging of foundation started
  • Digging of foundation completed
  • Laying of concrete started
  • Laying of concrete completed
  • All the above.
Q.16

The estimated time required to perform an activity, is known as

  • event
  • dummy
  • duration
  • float.
Q.17

Pick up the incorrect statement from the following:

  • The activity is the time consuming part of a project
  • The beginning and end of a job, are called events
  • The activity which consumes maximum time, is called a node
  • Logically and sequentially connected activities and events form a network
  • None of these.
Q.18

Pick up the correct statement from the following:

  • The float may be positive, zero or negative
  • If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
  • If the float of an activity is negative, delay in its performance is bound to delay the completion of project
  • If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
  • All the above.
Q.19

If the total float and duration of an activity are 5 anddays respectively, the particular activity can be

  • started 5 days later
  • completed 5 days later
  • performed at slower rate in 15 days
  • all the above.
Q.20

Critical path lies along the activities having total float

  • positive
  • negative
  • zero
  • same.