If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
The Overall in-charge of an organisation at the site responsible for the execution of the works, is
The main advantage of line organisation, is :
Pick up the correct statement from the following:
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
Modular co-ordination of construction means proper
PERT analysis is based on
Power stations are generally treated as
The critical activity has
Henry Gantt developed Bar charts for planning and scheduling of projects in
The final selection of a construction site, is done by
If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
For completion of a project, the critical path of the network represents
An event is indicated on the network by a number enclosed in
Which one of the following represents an event ?
The main disadvantage of line organisation, is
Please disable the adBlock and continue. Thank you.