Q.1
Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
Q.2
Which one of the following represents an event?
Q.3
The reduction in project time normally results in
Q.4
Site order book is used for recording
Q.5
Which of the following does not represent an activity?
Q.6
Which of the following earth moving machines has the shortest cycle time?
Q.7
A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be
Q.8
Sinking fund is
Q.9
Sensitivity analysis is a study of
Q.10
In resources levelling
Q.11
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
Q.12
The basic action involved in sheep foot rolling is
Q.13
Completion of an activity on CPM network diagram, is generally known
Q.14
Grader is used mainly for
Q.15
Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is
Q.16
While scheduling a project by C.P.M.
Q.17
Final technical authority of a project lies with
Q.18
The technique for establishing and maintaining priorities among the various jobs of a project, is known
Q.19
Select the correct statement.
Q.20
Select the incorrect statement.
Q.21
If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
Q.22
The constraints in case of resource smoothening operation would be
Q.23
Pick up the incorrect statement from the following:
Q.24
Pick up the correct statement from the following:
Q.25
Pick up the correct statement from the following:
Q.26
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
Q.27
Select the incorrect statement.
Q.28
Select the incorrect statement.
Q.29
Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control.
of following statements
Q.30
PERT is
0 h : 0 m : 1 s