Q.1
Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
Ice
Concrete
Loose sand
Earth
Q.2
Which one of the following represents an event?
Concrete cured
Fixing of door
Plastering of walls
Selecting sites
Q.3
The reduction in project time normally results in
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both
Decreasing the direct cost and indirect cost both
Q.4
Site order book is used for recording
Instructions by the executive engineers
Construction measurements
Issue of store equipments
Names of the casual labour
Q.5
Which of the following does not represent an activity?
Site located
Foundation is being dug
The office area is being cleaned
The invitations are being sent
Q.6
Which of the following earth moving machines has the shortest cycle time?
Drag line
Hoe
Clam shell
Dipper shovel
Q.7
A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be
3.7 years
4.23 years
5 years
7.87 years
Q.8
Sinking fund is
The fund for rebuilding a structure when its economic life is over
Raised to meet maintenance costs
The total sum to be paid to the municipal authorities by the tenants
A part of the money kept in reserve for providing additional structures and structural modifications
Q.9
Sensitivity analysis is a study of
Comparison of profit and loss
Comparison of assets and liabilities
Change in output due to change in input
Economics of cost and benefits of the project
Q.10
In resources levelling
Total duration of project is reduced
Total duration of project is increased
Uniform demand of resources is achieved
Cost of project is controlled
Q.11
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
3425 kg
5515 kg
4350 kg
2975 kg
Q.12
The basic action involved in sheep foot rolling is
Kneading
Pressing
Tamping
Vibration
Q.13
Completion of an activity on CPM network diagram, is generally known
Event
Node
Connector
All the above
Q.14
Grader is used mainly for
Trimming and finishing
Shaping and trimming
Finishing and shaping
Finishing, shaping and trimming
Q.15
Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is
1, 3, 2, 4
3, 1, 4, 2
3, 1, 2, 4
1, 3, 4, 2
Q.16
While scheduling a project by C.P.M.
A project is divided into various activities
Required time for each activity is established
Net work is drawn by connecting the activities and the events
All the above
Q.17
Final technical authority of a project lies with
Assistant Engineer
Executive Engineer
Superintending Engineer
Chief Engineer
Q.18
The technique for establishing and maintaining priorities among the various jobs of a project, is known
Event flow scheduling technique
Critical ratio scheduling
Slotting technique for scheduling
Short interval scheduling
Q.19
Select the correct statement.
Activity arrows in a CPM network are drawn to scale
The tail of an arrow represents the finish of an activity
Arrow bead represents the start of an activity
None of the above
Q.20
Select the incorrect statement.
Earliest start of an activity is the early event time of the node it leaves
Latest finish of an activity is the late event time of the node it enters
Latest start of an activity is its latest finish minus its duration
None of the above
Q.21
If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
2.3% and 84.1%
97.7% and 84.1%
97.7 % and 15.9%
15.9% and 97.7%
Q.22
The constraints in case of resource smoothening operation would be
Resources
Project duration time
Both resources and project duration time
None of the above
Q.23
Pick up the incorrect statement from the following:
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
The difference between the maximum time available for the job and actual time it consumes, is called total float
The difference between the latest start time and earliest start time of an activity, is called total float
None of these
Q.24
Pick up the correct statement from the following:
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
Q.25
Pick up the correct statement from the following:
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The difference between total float and free float, is called interfering float
All the above
Q.26
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
Started 5 days later
Completed 5 days later
Performed at slower rate in 15 days
All the above
Q.27
Select the incorrect statement.
Start float and finish float are always equal
Total float can be either start float or finish float
Start float and finish float need not be equal
Start float and finish float are the differences between activity times and not event times
Q.28
Select the incorrect statement.
A critical path always begins at the very first event.
A critical path always terminates at the last event.
Critical activities control the project duration.
Critical activity is the one for which free float is zero.
Q.29
Wheeled tractors are replacing crawler tractors because
1. Wheeled tractors travel faster.
2. Crawler tractors are more expensive.
3. Track parts of a crawler wear out quickly.
4. Crawler tractors have stick control.
of following statements
1, 3 and 4 are correct
2, 3 and 4 are correct
1, 2 and 3 are correct
1, 2 and 4 are correct
Q.30
PERT is
An analytic in concept
Limited of event oriented diagrams
Used for research and development projects
All the above
0 h : 0 m : 1 s
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Report Question
×
What's an issue?
Question is wrong
Answer is wrong
Other Reason