Q.1
Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
Q.2
The salient feature of functional organization is
Strict adherence to specifications
Separation of planning and design part
Each individual maintains functional efficiency
All the above
Q.3
The time corresponding to minimum total project cost is
Crash time
Normal time
Optimistic time
Between normal time and crash time
Q.4
Residential buildings are treated as
Light construction
Heavy construction
Industrial construction
Private construction
Q.5
Output of a bulldozer is
(i) Increased if drawbar HP of the tractor is increased for a given hauling distance
(ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance
(iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor
(iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
(i) and (iii) are correct
(i) and (iv) are correct
(ii) and (iii) are correct
(ii) and (iv) are correct
Q.6
The critical activity has
Maximum float
Minimum float
Zero float
None of these
Q.7
Pick up the incorrect statement from the following:
The activity is the time consuming part of a project
The beginning and end of a job, are called events
The activity which consumes maximum time, is called a node
Logically and sequentially connected activities and events form a network
Q.8
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
19
14
24
None of these
Q.9
The part of a derrick crane include
(i) Mast
(ii) Boom
(iii) Bull wheel
(iv) Jack
which of these statements are correct?
(i), (ii) and (iv) are correct
(ii), (iii) and (iv) are correct
(i), (iii) and (iv) are correct
(i), (ii) and (iii) are correct
Q.10
For excavating utility trenches with precise control of depth, the excavation equipment used is
Hoe
Shovel
Dragline
None of the above
Q.11
For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
Moist loam
Good common earth
Well blasted rock
Wet sticky clay
Q.12
The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be
Rs. 8,800
Rs. 7,600
Rs. 6,400
Rs. 5,000
Q.13
Crash project duration is obtained by summing the
Normal durations for all the activities
Crash durations for all activities
Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Q.14
Preliminary project report for a road project must contain
The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders
Q.15
The process of incorporating changes and rescheduling or replanning is called
Resource levelling
Resource smoothening
Updating
Critical path scheduling
Q.16
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
EF = ES + D
LS = LF - D
LF = LS + D
All the above
Q.17
The object of technical planning, is
Preparation of specifications
Preparation of estimates
Initiating the procurement action of resources
All the above
Q.18
Total float for any activity is defined as the difference between
Its latest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest start time and earliest finish time
Its earliest finish time and earliest start time for its successor activity
Q.19
Which of the following is a weakness of bar chart?
Interdependencies of activities
Project progress
Uncertainties
All of the above
Q.20
For completion of a project, the critical path of the network represents
Minimum time
Maximum time
Maximum cost
Minimum cost
Q.21
The most popular type of organization used for Civil Engineering Constructions, is
Line organization
Line and staff organization
Functional organization
Effective organization
Q.22
CPM is
Synthesising in concepts
Is built of activities oriented programme
Is based on time estimate
All the above
Q.23
Military organization is known as
Line organization
Line and staff organization
Functional organization
None of these
Q.24
Critical path lies along the activities having total float
Positive
Negative
Zero
Same
Q.25
Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
Concrete
Loose sand
Asphalt
Firm earth
Q.26
Power stations are generally treated as
Light construction
Heavy construction
Industrial construction
Electrical construction
Q.27
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then
expected time of activity A is greater than the expected time of activity B
expected time of activity B is greater than the expected time of activity A
expected time of both activities A and B are same
none of the above
Q.28
Mile Stone charts were invented in the year of
1910
1920
1930
1940
Q.29
Which one of the following represents an activity?
Excavation for foundation
Curing of concrete
Setting of question paper
All the above
Q.30
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
Rs. 4,75,000
Rs. 5,75,000
Rs. 6,50,000
Rs. 8,50,000
0 h : 0 m : 1 s
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Report Question
×
What's an issue?
Question is wrong
Answer is wrong
Other Reason
Want to elaborate a bit more? (optional)
Support mcqgeeks.com by disabling your adblocker.
×
Please disable the adBlock and continue.
Thank you.
Reload page