Q.1
Which of the following excavators is most suitable for digging under water?
Drag line
Hoe
Clam shell
Dipper shovel
Q.2
In time-cost optimization of a project, crashing is done.
On all the activities
On all the activities lying on the critical path
Only on activities lying on the original critical path and having flatter cost slopes
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Q.3
Critical path
Is always longest
Is always shortest
May be longest
May be shortest
Q.4
An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is
Rs. 8,43,750
Rs. 8,75,000
Rs. 10,50,000
Rs. 11,56,250
Q.5
Slack time refers to
An activity
An event
Both event and activity
None of the above
Q.6
A dummy activity
Is artificially introduced
Is represented by a dotted line
Does not consume time
All the above
Q.7
A Milestone chart
Shows the interdependencies of various jobs
Depicts the delay of jobs, if any
Points outgoing ahead of schedule of jobs, if any
None of these
Q.8
Latest start of an activity is always
greater than or equal to latest event time of preceding node
less than or equal to latest event time of preceding node
equal to latest event time of preceding node
less than latest event time of preceding node
Q.9
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
20
25
35
15
Q.10
Rolling resistance of a wheel depends upon
(i) Vehicle load
(ii) Grade
(iii) Ground conditions
Only (i) is correct
(i) and (ii) are correct
(i) and (iii) are correct
(ii) and (iii) are correct
Q.11
Earliest finish of an activity is always
Greater than earliest event time of the following node
Less than earliest event time of the following node
Less than or equal to earliest event time of the following node
Greater than or equal to earliest event time of the following node
Q.12
The most suitable type of equipment for compaction of cohesive soils is
Smooth-wheeled rollers
Vibratory rollers
Sheep foot rollers
Tampers
Q.13
Frederick W. Taylor introduced a system of working known as
Line organization
Line and staff organization
Functional organization
Effective organization
Q.14
For the execution of a project, a contractor is
A person
A firm
An agency
All the above
Q.15
An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
Rs. 31050
Rs. 34500
Rs. 37950
Rs. 50000
Q.16
Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project
PERT is preferred for planning because of
1, 2 and 4
3, 4 and 5
1, 3 and 4
1, 2 and 5
Q.17
Consider the following statements:
In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated.
1, 2 and 3 are correct
1 and 4 are correct
2, 3 and 4 are correct
1, 2 and 4 are correct
Q.18
Batching refers to
Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Q.19
The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively
80 and 90
90 and 80
85 and 75
75 and 83
Q.20
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
Longest duration
Highest cost slope
Least cost slope
Shortest duration
Q.21
A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
Rs. 1740
Rs. 3480
Rs. 5220
Rs. 6960
Q.22
The main disadvantage of line organization, is
Rigid structure
Extraordinary delay in communications
Top level executions over work
All the above
Q.23
The main principle of an organization, is
Unity of command
Effective control at all levels
Delegation of authority
All the above
Q.24
Time and progress chart of a construction, is also known as
Bar chart
Gantt chart
Modified Mile stone chart
All the above
Q.25
The difference between the time avail-to do a job and the time required to do the job, is known as
Event
Float
Duration
Constraint
Q.26
The Overall in-charge of an organization at the site responsible for the execution of the works, is
Executive Engineer
Engineer
Junior Engineer
Assistant Engineer
Q.27
In the given figure, the network of a project represents
Activity of an excavation of a footing
Activity of an excavation which starts at event No. 1 and ends at even No. 2
Activity of excavation which takes 8 units of time
None of these
Q.28
Works costing less than Rs. 20,000 are treated as
Any project
Major projects
Minor projects
All the above
Q.29
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
4 days
6 days
10 days
16 days
Q.30
Consider the following statements for a power shovel:
(i) Output can be increased by reducing the angle of swing for a given depth of cut.
(ii) For a given angle of swing, output will be maximum at optimum depth of cut.
(iii) Output can be increased by keeping the depth of cut less than optimum depth.
(iv) Output can be increased by increasing the size of shovel.
(ii), (iii) and (iv) are correct
(i), (ii) and (iv) are correct
(i), (iii) and (iv) are correct
(i) and (iv) are correct
0 h : 0 m : 1 s
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Report Question
×
What's an issue?
Question is wrong
Answer is wrong
Other Reason
Want to elaborate a bit more? (optional)
Support mcqgeeks.com by disabling your adblocker.
×
Please disable the adBlock and continue.
Thank you.
Reload page