MCQGeeks
0 : 0 : 1
CBSE
JEE
NTSE
NEET
English
UK Quiz
Quiz
Driving Test
Practice
Games
Quiz
Civil Engineering
Construction Project Management
Quiz 2
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Q.1
The major differences between projects and operations are:
Projects are ongoing and operations are short
Projects should always be done by engineers and operations may be performed by technicians
Projects are temporary and operations are ongoing
Projects and operations are the same thing but projects always costs more to implement
Q.2
The Overall in-charge of an organisation at the site responsible for the execution of the works, is
Executive Engineer
Engineer
Junior Engineer
Sub overseer
Q.3
The time which results in the leasi, possible construction cost of an activity, is known
normal time
slow time
crash time
standard time.
Q.4
Site order book is used for recording
instructions by the executive engineers
construction measurements
issue of store equipments
names of the casual labour.
Q.5
Construction team means
an engineer
an architect
an owner
a contractor
all the above.
Q.6
Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:
1. Pouring of Concrete 2. Erection of form work 3. Curing of concrete 4. Removal of form work
1. Erection of form work 2. Pouring of concrete 3. Curing of concrete 4. Removal of form work
1. Removal of form work 2. Erection of form work 3. Pouring of concrete 4. Curing of concrete
1. Pouring of concrete 2. Curing of concrete 3. Erection of form work 4. Removal of form work
Q.7
Critical path method
is an improvement upon bar chart method
provides a realistic approach to daily problems
avoids delays which are very common in bar charts
was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S. in 1957
All the above.
Q.8
The salient feature of functional organisation is
strict adherence to specifications
separation of planning and design part
each individual maintains functional efficiency
work is properly planned and distributed
E. all the above.
Q.9
The most popular type of organisation used for Civil Engineering Constructions, is
line organisation
line and staff organisation
functional organisation
effective organisation.
Q.10
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
duration
total flat
free float
interfering float.
Q.11
Military organisation is known as
line organisation
line and staff organisation
functional organisation
none of these.
Q.12
Critical Path Net Work helps an engineer
to concentrate his attention on critical activities
to divert the resources from non-critical advanced activities to critical activities
to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
all the above.
Q.13
Pick up the PERT event from the following:
Digging of foundation started
Digging of foundation completed
Laying of concrete started
Laying of concrete completed
All the above.
Q.14
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
EF = ES + D
LS = LF - D
LF = LS + D
D = EF - ES
all the above.
Q.15
Final technical authority of a project lies with
Assistant Engineer
Executive Engineer
Superintending Engineer
Chief Engineer.
Q.16
The technique for establishing and maintaining priorities among the various jobs of a project, is known
Event flow scheduling technique
Critical ratio scheduling
Slotting technique for scheduling
Short interval scheduling.
Q.17
During which phase of a project is the project plan most closely monitored?
Design phase
Planning and analysis phase
Implementation or publishing phase
Building and testing phase
Q.18
Characteristic of construction management are ....i) Complex and it involves a number of individuals from different departments. ii) Unique and cannot be replicated.iii) Consists of a number of associated activities iv) Satisfy the owners requirement and expectations from the project.
i and ii
i and iii
ii, iii and iv
i, ii, iii and iv
Q.19
Local authorities during construction are....i) Tenaga Nasional Berhadii) Telekom Malaysiaiii) Jabatan Bomba & Penyelamativ) Indah Water Konsortium
ii, iii dan iv
i and iii
i and iv
i, ii, iii and iv
Q.20
Parties involved during the construction except
Supplier
Authorities
FInancial company
Jabatan Kerja Raya
0 h : 0 m : 1 s
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Report Question
×
What's an issue?
Question is wrong
Answer is wrong
Other Reason
Want to elaborate a bit more? (optional)
Support mcqgeeks.com by disabling your adblocker.
×
Please disable the adBlock and continue.
Thank you.
Reload page