Q.1

Pick up the correct statement from the following:

  • If the bed level is above N.S.L. the canal is called fully in baking and the berms are designed as 3 d where d is full supply depth of water (F.S.D.)
  • Area of canal in cutting = BD + Sd2 where B = bed width, d = depth of cutting and S is the side slope
  • Area of the bank of canal = B1d1 + Sd2 where B1, d1 and S are the width of bank, height of the bank above N.S.L. and side slope respectively
  • If F.S.L. is above N.S.L the canal is called partly in cutting and partly in filling and berms are designed as 2d where d is full supply depth
  • All the above.
Q.2

Pick up the correct statement from the following:

  • Bricks are paid per thousand
  • Cement is paid per 50 kg bag
  • Lime is paid per quintal
  • Brick aggregates is paid per cum
  • All the above.
Q.3

The floor area includes the area of the balcony up to

  • 100%
  • 75%
  • 50%
  • 25%
Q.4

The measurement is made for stone work in square metre in case of

  • Wall facing
  • Columns, lintels, copings
  • Building work
  • Dressed stones in Chajjas
  • (a) and (d) of the above.
Q.5

The following item of earth work is not measured separately.

  • Setting out of works
  • Site clearence
  • dead men
  • Steps in deep exavaction
  • All the above.
Q.6

The weight of an item is measured correct to nearest

  • 0.25 kg
  • 0.50 kg
  • 0.75 kg
  • 1.00 kg
  • 5 kg
Q.7

The 'centre line method' is specially adopted for estimating

  • Circular buildings
  • Hexagonal buildings
  • Octagonal buildings
  • Other geometrical shaped buildings
  • All the above.
Q.8

The value of 'A' of Indian type W.C. shown in the given figure is :

  • 25 cm
  • 30 cm
  • 40 cm
  • 45 cm
Q.9

The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is

Q.10

The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is

Q.11
The most reliable estimate is
  • Detailed estimate
  • Preliminary estimate
  • Plinth area estimate
  • Cube rate estimate
Q.12
The plinth area of a building not includes
  • Area of the walls at the floor level
  • Internal shaft for sanitary installations up to 2 sq m. in area
  • Lift and wall including landing
  • Area of cantilevered porch
Q.13
Carpet area does not include the area of
  • The walls along with doors and other openings
  • Bath room and lavatory
  • Kitchen and pantry
  • None of the above
Q.14
The measurement is not made in square meters in case of
  • P. (Damp proof course)
  • Form works
  • Concrete Jeffries
  • R. Chhajja
Q.15
The diameter of a domestic sewer pipe laid at gradient 1 inis recommended
  • 100 mm
  • 150 mm
  • 200 mm
  • 175 mm
Q.16
Pick up the item of work not included in the plinth area estimate
  • Wall thickness
  • Room area
  • W' Area
  • Courtyard area
Q.17
While preparing a detailed estimate
  • Dimension should be measured correct to 0.01 m
  • Area should be measured correct to 0.01 sqm
  • Volume should be measured correct to 0.01 cum
  • All the above
Q.18
The order of booking dimensions is
  • Length, breadth, height
  • Breadth, length, height
  • Height, breadth, length
  • None of these
Q.19
The brick work is not measured in cu m in case of
  • One or more than one brick wall
  • Brick work in arches
  • Reinforced brick work
  • Half brick wall
Q.20
The area is measured correct to the nearest
  • 0.01 sqm
  • 0.02 sqm
  • 0.03 sqm
  • 0.04 sqm
Q.21
The measurement is made for stone work in square metre in case of
  • Wall facing
  • Columns, lintels, copings
  • Building work
  • (A) and (B) of the above
Q.22
The measurement is made in square metre in case of
  • Cement concrete in foundation
  • R. structure
  • Hollow concrete block wall
  • None of these
Q.23
The volume is measured correct to the nearest
  • 0.01 cum
  • 0.02 cum
  • 0.03 cum
  • 0.04 cum
Q.24
Pick up the correct statement regarding the centre line method of estimating a building
  • Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item
  • The centre line is worked out separately for different sections of walls of a building
  • The centre line length is reduced by half the layer of main wall joining the partition wall
  • All the above
Q.25
The expected out turn of half brick partition wall per mason per day is
  • 1.5 m2
  • 2.0 m2
  • 4.0 m2
  • 5.0 m2
Q.26
The expected out turn ofmm plastering with cement mortar is
  • 2.5 sq m
  • 4.0 sq m
  • 6.0 sq m
  • 8.0 sq m
Q.27
The inspection pit or chamber is a manhole provided in a base drainage system
  • At every change of direction
  • At every change of gradient
  • At every 30 m intervals
  • All the above
Q.28
The concrete work for the following part of the building of specified thickness is measured in square meters
  • Root slabs
  • Floors
  • Wall panels
  • All the above
Q.29
Pick up the incorrect statement regarding a master trap from the following:
  • It is provided in between the lower end of the house drain and the street sewer
  • It is provided a cleaning eye at the top of the trap
  • The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe
  • The water seal is less than that of ordinary traps
Q.30
A cement concrete road ism long, 8 m wide andcm thick over the sub-base ofcm thick gravel. The box cutting in road crust is
  • 500 m3
  • 1000 m3
  • 1500 m3
  • 2000 m3
0 h : 0 m : 1 s