Q.1
The canal alignment is finalized only after finalizing the CD works.
  • a) True
  • b) False
Q.2
The relative bed levels of the canal and the drainage may be changed and manipulated by _________________
  • a) changing the alignment
  • b) changing the positions of the water table
  • c) altering the head level
  • d) use of dewatering equipment
Q.3
The selection of the CD works depends on?
  • a) i and ii
  • b) i, ii and iv
  • c) i, ii and iii
  • d) i, ii, iii and iv
Q.4
Inlets and Outlets are inferior to aqueduct or super-passage type of work.
  • a) True
  • b) False
Q.5
In order to reduce the CD works, the artificial canals are generally aligned along the ridgeline.
  • a) True
  • b) False
Q.6
The type of canal alignment which involves maximum CD works is a ______________
  • a) ridge canal
  • b) contour canal
  • c) side slope canal
  • d) both ridge and contour canal