Q.1
Work sampling is applied for
Q.2
Which of the following equations is not in conformity with others?
Q.3
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
Q.4
The assumption in PERT is
Q.5
Bin card is used in
Q.6
Acceptance sampling is used in
Q.7
The performance of a specific task in CPM is known as
Q.8
Line organization is suitable for
Q.9
Work sampling observations are taken on the basis of
Q.10
Break-even analysis consists of
Q.11
PERT analysis is based on
Q.12
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
Q.13
A CPM family includes
Q.14
M.T.M. is used to
Q.15
In a line organization
Q.16
The value engineering technique in which experts of the same rank assemble for product development is called
Q.17
What does symbol 'V' employ in work study
Q.18
What does symbol 'D' imply in work study?
Q.19
What does symbol 'O' imply in work study?
Q.20
The salient feature of functional organisation is
Q.21
The time which results in the least possible direct cost of an activity is known as
Q.22
The grouping of activities into organizational units is called
Q.23
If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
Q.24
When slack of an activity is negative
Q.25
When slack of an activity is positive
Q.26
The two bin system is concerned with
Q.27
Work study is concerned with
Q.28
The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as
Q.29
In time study, the rating factor is applied to determine
Q.30
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
0 h : 0 m : 1 s