MCQGeeks
0 : 0 : 1
CBSE
JEE
NTSE
NEET
English
UK Quiz
Quiz
Driving Test
Practice
Games
Practice
Ch 3 Quiz
«
Multiple Choice Questions
»
1
2
3
Activity D on a CPM network has predecessors B and C, and has successor F. D has durationB's earliest finish is 18, while C's isF's late start isWhich of the following is true? a. B is a critical activity. b. C is completed before B. c. D has no slack but is not critical. d. D is critical, and has zero slack. e. All of the above are true.
0%
One; $400
0%
D
0%
B
0%
A
A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8.a. The critical path is D-E-F, durationb. The critical path is D-F, durationc. Slack at D is 3 units d. Slack at E is 3 units e. Both a and c are true
0%
D
0%
B
0%
A
0%
One; $400
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8.a. The critical path is A-B-C, durationb. The critical path is A-C, durationc. The critical path is A-B-C, duration 13.5 d. The critical path cannot be determined without knowing PERT expected activity times. e. The network has no critical path.
0%
A
0%
B
0%
D
0%
Beta
0 h : 0 m : 1 s
«
Multiple Choice Questions
»
1
2
3
0
Answered
0
Not Answered
0
Not Visited
Correct : 0
Incorrect : 0
Report Question
×
What's an issue?
Question is wrong
Answer is wrong
Other Reason
Want to elaborate a bit more? (optional)
Support mcqgeeks.com by disabling your adblocker.
×
Please disable the adBlock and continue.
Thank you.
Reload page