MCQGeeks
0 : 0 : 1
CBSE
JEE
NTSE
NEET
English
UK Quiz
Quiz
Driving Test
Practice
Games
Practice
Project Cost Management - Ch 7 (True/False) Quiz
«
Multiple Choice Questions
»
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Overrun is the additional percentage amount by which estimates exceed actual costs.
0%
True
0%
False
IT project managers must be able to present and discuss project information both in financial and technical terms.
0%
True
0%
False
Determining the budget involves allocating the project cost estimate to individual work items over time.
0%
True
0%
False
Parametric models are reliable when the models are flexible in terms of the project's size.
0%
True
0%
False
Analogous estimates are called activity based costing.
0%
True
0%
False
If the cost performance index (CPI) is less than 100 percent, the project is under budget.
0%
True
0%
False
Analogous estimates are the most accurate technique to estimate costs.
0%
True
0%
False
Budgetary estimates are made even before a project is officially started.
0%
True
0%
False
A schedule performance index of one means that the project is on schedule.
0%
True
0%
False
A cost management plan can include organizational procedures links, control thresholds, and process descriptions.
0%
True
0%
False
Contingency reserves are also known as unknown unknowns.
0%
True
0%
False
Supporting details for an estimate include the ground rules and assumptions used in creating the estimate.
0%
True
0%
False
A budgetary estimate is the most accurate of the three types of estimates.
0%
True
0%
False
In a bottom up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates.
0%
True
0%
False
The primary output of the planning cost management process is a change request.
0%
True
0%
False
Definitive estimates are made one year or less prior to project completion.
0%
True
0%
False
Project managers must conduct cash flow analysis to determine net present value.
0%
True
0%
False
When deciding what projects to invest in or continue, one should include sunk costs.
0%
True
0%
False
Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.
0%
True
0%
False
If cost variance is a positive number, it means that performing the work costs more than planned.
0%
True
0%
False
A negative schedule variance means that it took lesser than planned to perform the work.
0%
True
0%
False
0 h : 0 m : 1 s
«
Multiple Choice Questions
»
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
0
Answered
0
Not Answered
0
Not Visited
Correct : 0
Incorrect : 0
Report Question
×
What's an issue?
Question is wrong
Answer is wrong
Other Reason
Want to elaborate a bit more? (optional)
Support mcqgeeks.com by disabling your adblocker.
×
Please disable the adBlock and continue.
Thank you.
Reload page