MCQGeeks
0 : 0 : 1
CBSE
JEE
NTSE
NEET
English
UK Quiz
Quiz
Driving Test
Practice
Games
Practice
Scms331 Chapter 3 Quiz
«
Multiple Choice Questions
»
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PERT analysis computes the variance of the total project completion time as:
0%
The sum of the variances of all activities on the critical path.
0%
Planning, scheduling, and controlling
0%
Only critical activities contribute to the project variances.
0%
are used when two activities have identical starting and ending events.
An activity on a PERT network has these time estimates: optimistic =2, most likely = 3, and pessimisticIts expected time and variance (if it is a critical activity) are:
0%
Slack time
0%
3.67 and 1
0%
19 days
0%
Early Start
An activity has an optimistic time of 15 days, a most likely time of 18 days, and a pessimistic time of 27 days. What is the expected time?
0%
3.67 and 1
0%
19 days
0%
Early Start
0%
Slack time
With respect to PERT and CPM, slack__________
0%
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
0%
Gantt charts are visual devices that show the duration of activities in a project.
0%
is the amount of time a task may be delayed without changing the overall project completion time.
0%
because near-critical paths could become critical paths with small delays in these activities
The Beta distribution is used in project management to
0%
longest time path through the network
0%
No activity in the network must be repeated.
0%
calculate expected activity times
0%
Planning, scheduling, and controlling
The three phases involved in the management of large projects are:
0%
longest time path through the network
0%
Planning, scheduling, and controlling
0%
calculate expected activity times
0%
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
__________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.
0%
3.67 and 1
0%
19 days
0%
Slack time
0%
Early Start
An activity has an optimistic time of 11 days, a most likely time of 15 days, and a pessimistic time of 23 days. What is its variance?
0%
5.33
0%
4
0%
1.22
0%
2.33
In a PERT network, non-critical activities that have little slack need to be monitored closely__________
0%
because near-critical paths could become critical paths with small delays in these activities
0%
is the amount of time a task may be delayed without changing the overall project completion time.
0%
Gantt charts are visual devices that show the duration of activities in a project.
0%
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
The EF of an activity is the:
0%
No activity in the network must be repeated.
0%
Early Start
0%
ES + Activity Time
0%
longest time path through the network
A project's critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?
0%
2.33
0%
4
0%
1.22
0%
5.33
Dummy activities__________
0%
The sum of the variances of all activities on the critical path.
0%
is the amount of time a task may be delayed without changing the overall project completion time.
0%
are used when two activities have identical starting and ending events.
0%
because near-critical paths could become critical paths with small delays in these activities
Which of the following statements regarding PERT analysis is true?
0%
Only critical activities contribute to the project variances.
0%
Early Start
0%
Gantt charts are visual devices that show the duration of activities in a project.
0%
No activity in the network must be repeated.
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario, how many networks are in this path?
0%
Planning, scheduling, and controlling
0%
There are four paths in the network.
0%
Work Breakdown Structure
0%
calculate expected activity times
0 h : 0 m : 1 s
«
Multiple Choice Questions
»
1
2
3
4
5
6
7
8
9
10
11
12
13
14
0
Answered
0
Not Answered
0
Not Visited
Correct : 0
Incorrect : 0
Report Question
×
What's an issue?
Question is wrong
Answer is wrong
Other Reason
Want to elaborate a bit more? (optional)
Support mcqgeeks.com by disabling your adblocker.
×
Please disable the adBlock and continue.
Thank you.
Reload page